restoration">

 

Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Project Equipment
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

The water depth in the placement area ranged from 4 to 6 ft. The dike, adja-
cent pasture uplands, and wetlands separating the river and the placement area
were approximately 900 ft wide consisting of a rock face adjacent to the river and
the remainder a sandy soil with a maximum elevation approximately 2 to 3 ft
above the river surface. The soil portion of the pasture was vegetated with short
grass, small bushes, and marsh grass adjacent to the open water on the west side.
River vessel traffic during the demonstration project was typical according to the
river pilots. Vessel traffic averaged 20 to 25 deep-draft vessels per 24-hr period.
The passing vessel traffic was not evenly spaced. Several times during the
project, two deep-draft vessels passed abreast in the area of the channel where the
Beachbuilder was working (Photo 1). There were periods of up to 3 hr with no
deep-draft vessel traffic. The deep-draft vessel traffic tended to navigate toward
the outside of the bend, or left descending bank (LDB) side of the channel, while
making their turn into or out of Southwest Pass. Due to cross currents caused by
flows into Pass A Loutre and South Pass, pilots on the deep-draft vessels going
downstream tend to swing the vessels' bows more toward the right descending
bank (RDB) side (thereby occupying more of the channel cross section while
crabbing around the bend entering Southwest Pass) to compensate for the ships'
tendency to be pulled toward the LDB side of the channel (see illustration in
Figure 4).
The U.S. Coast Guard posted a Notice to Mariners about the demonstration.
Shallow-draft vessel traffic consisted of tugs, shrimp boats, work boats, fishing
boats, and pleasure boats. This vessel traffic moved unimpeded both in and out of
the channel during dredging operations. Outside the channel, shallow-draft vessel
traffic moved across the submerged line that ran along the RDB side of the river
up to the shoreline. No count of shallow-draft vessel traffic was maintained
during the project.
Atmospheric conditions during the demonstration project were typical for the
season and recorded in the daily Report of Operations Engineer Form 4267. Day-
time temperatures ranged from the upper 80's to lower 90's (degrees Fahrenheit).
Periodic thundershowers were prevalent in the afternoons. Winds were generally
light to moderate (maximum of 10 knots) with gusts associated with thunder-
showers. Visibility during the demonstration was approximately 10 miles with no
occurrence of significant fog events.
Project Equipment
The dustpan dredge Beachbuilder used for the demonstration project is a
nonself-propelled dredge. The dredge hull is approximately 300 ft long and 75 ft
wide (see Photo 2). The maximum draft of the dredge is approximately 8.5 ft.
The maximum dredging depth of the Beachbuilder is approximately 70 ft with a
ladder length of 104 ft. The dustpan head is 40 ft wide (see Photo 3). The ladder
on the Beachbuilder is equipped with a submerged pump that transfers the sedi-
ment from the head to twin pumps on deck (see Photos 4 and 5). Total pumping
horsepower capability is approximately 9,000 hp (two 3,600-hp dredge pumps
9
Chapter 2
Project Description

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business