restoration">

 

Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Project Operations
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

anchors slipping, the Delta Eagle was replaced by the Delta Pacer (4,200 hp; see
Photo 17). The Delta Eagle was then connected to the starboard side of the
Beachbuilder to help maneuver the dredge in and out of the channel. The Delta
Eagle was later replaced with the Matthew (3,000 hp; see Photo 18), a Weeks
Marine tug. Two smaller tugs, the Delta Fox (900 hp; see Photo 19) and Delta
Robin (600 hp; see Photo 20), were used to move several support barges
including one equipped with a 55-ton capacity crane (Weeks 553) used to lift
pipe (see Photo 21) and a small A-frame barge (or stiff-leg derrick) used to move
anchors and the hard point (see Photo 22). The tugs were also used to hold the
floating hose in position. A small tug, the Marie (300 hp; see Photo 23), was
used to ferry personnel and help move the small barges.
Additional equipment included a quarters barge for Weeks Marine personnel
equipped with a galley where meals were prepared (see Photo 24). The quarters
barge was anchored in South Pass just below the HOP. Two 42-ft crew boats, the
Cheyenne and the Flying Cloud, were used to transport Corps, OAS, and Weeks
Marine personnel along with visitors between Venice, the Beachbuilder, the dike
near the placement area, and the quarters boat. The hydrographic survey boat
used by Weeks Marine was the Sabine and the MVN daily channel surveys were
conducted by the John Bopp, W-46, Laborde, and OB-173.
Project Operations
3 and 4 June 2002
As previously noted, Weeks Marine initiated mobilization activities during
the last week of May 2002. Mobilization activities continued after the kick-off
meeting on 3 June. Before-dredging (BD) surveys of the three river channel
reaches and the placement areas in the marsh were conducted by the contractor.
On 3 and 4 June, Weeks personnel completed laying the submerged line and
extended the shore line across the dike, pasture, and existing wetlands and into
the designated placement area.
5 June 2002
On 5 June, Weeks personnel set the hard point to work in Reach 1 and con-
nected the floating hose to the hard point (see Photo 25) and the Beachbuilder
discharge line. Water was pumped through the floating hose, submerged line, and
shore line pipe to the placement area to test pumps and piping connections.
Weeks personnel, accompanied by an MVN inspector, surveyed the submerged
line elevations to confirm that the pipeline had not caused any shoaling or scour
to occur.
During the afternoon, the Beachbuilder's wire cable was extended and the
anchors set. Although the winches could spool approximately 2,500 ft of 1.5-in.-
thick wire rope, no more than 2,200 ft was unspooled during the demonstration.
Conventional dustpan dredges typically spool longer wire lengths (i.e., 5,000-ft
lengths). Initially, five anchors were set. Three anchors were set upstream of the
12
Chapter 2
Project Description

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business