|
|
ERDC TN-DOER-E7
April 2000
RESULTS
Mobile Bay, Alabama. In January 1999, the U.S. Army Corps of Engineers hopper dredge
Wheeler dredged a portion of the upper reach of the main navigation channel in Mobile Bay (Fig-
ure 1). The dredging operation took approximately 30 min. Figure 2 shows the transects over which
measurements were made along the main Mobile Bay navigation channel, and the track the Wheeler
took while dredging. Transects 1 and 2 occurred before the Wheeler began dredging, while
Transect 8 occurred after the Wheeler had finished dredging. In addition to these transects, four
additional transects were run after the Wheeler had cleared the area, at approximately the same
location as Transect 1. Data from Transect 1 were used when the acoustic background was
subtracted from the measurements made while monitoring the plume, and the four transects run
after the Wheeler left the area were used to determine the background acoustic backscatter variations
unrelated to the dredging. Data from Transect 1 were subtracted from measurements made along
Transects 2 through 8 by using data from equivalent depths (i.e., from the same bin), and for the
same longitude plus or minus 0.0005 min of longitude. This means that each pair of values (i.e.,
monitoring measurement and background measurement) is from the same position across the
channel within approximately 2 m. The results were then divided by the standard deviation for the
equivalent depth, determined from the four transects made after the Wheeler left the area, resulting
Figure 2. Wheeler monitoring transects
4
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |