|
|
ERDC TN-DOER-I3
July 2000
Application of Dredge Monitoring Systems
to Dredge Contract Administration
Quality Assurance
PURPOSE: Monitoring technology is available for providing dredge process data to dredge
contract administrators during the course of a dredging contract. The U.S. Army Corps of Engineers
(USACE) contracts out more than 80 percent of all dredging under their jurisdiction. Presently,
Corps District offices have taken on more of a contract administration role rather than a technical
"hands on" role for insuring that the nation's waterways remain open and are navigable. Although
Corps inspectors are generally aboard the contractor's dredge during the dredging, the contract
administrator does not have direct access to dredge process data for evaluating the contractor's
performance. This technical note describes dredge-monitoring systems designed to provide contract
administrators with dredge process data for evaluating dredge productivity, efficiency, and overall
performance.
BACKGROUND: Generally, there are two types of dredging contracts: a lease dredge contract,
and a yardage contract. Payment of the lease dredge contract is based on an estimation of the time
required to remove an estimated amount of sediment from the project area. The primary consid-
eration for the cost of this work is the production capability of the dredge plant in removing cubic
yards of in place material per hour, and the hourly cost of the plant. The contracting officer is
responsible for insuring that the contracting dredge operates efficiently and maintains a reasonable
production rate over the project duration to insure that the terms of the contract are met. Typically,
the progress of the contractor dredge is gauged by post-dredging surveys which indicate if the
channel has been cleared to project depth. Potential disputes arise between the contractor and the
Corps concerning the rate the work is performed, i.e., if the dredging extends past the time specified
in the contract for completion of the job. In some cases, changing site conditions, such as sediment
variations or adverse weather or project site conditions will affect the work performance rate. If
conditions are encountered that affect the ability of the contractor to perform as specified in the
contract the contracting officer should be aware of these conditions within a reasonable time to
adjust the terms of the contract, and prevent costly litigation. Additional monitoring tools are needed
by contract administrators to judge if the dredge is operating efficiently and maintaining a reasonable
production rate.
The cubic yard contract provides payment to the contractor based on pre- and post-dredging surveys.
In this contract, the dredge contractor is paid by the volume of material removed, with the price per
unit volume negotiated in the contract. This price reflects the contractor's operating costs as well
as the profit margin. The primary consideration for this type contract is the accuracy and
dependability of the pre- and post-dredging surveys. The pre-dredging survey provides an estimate
of the material to be removed. In river systems, the river bed is constantly moving and changing,
sometimes drastically affecting the shoaling rate. During the time elapsed between the pre-dredging
survey and the contract bid and award, significant shoaling can occur, thus the pre-dredge survey
will underestimate the amount of material to be removed. Also, if the post-dredge survey is not
performed in a timely manner, additional shoaling can occur, thus again underestimating the amount
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |