|
|
Technical Note DOER-N3
March 1998
relatively higher mob/demob costs because those dredges require tugs to move, support vessels to
transport pipe or barges, and in some cases, land-based equipment for reworking of the placed
dredged material. Hopper dredges placing dredged material in open water typically have lower
mob/demob costs because a hopper dredge is an oceangoing vessel requiring less support.
However, if a hopper dredge is placing material via a direct pump-out buoy, mob/demob costs could
be comparable with mechanical and pipeline dredges.
Hopper dredges placing material nearshore by bottom discharge can help minimize overall dredging
project costs in two ways: (a) the lower mob/demob cost becomes more attractive (relative to other
dredge types); and (b) shorter haul distance to the nearshore placement site saves time and fuel
costs. Pipeline dredges can also reduce overall dredging project costs by placing material nearshore.
A pipeline dredge discharging into the nearshore reduces its own mob/demob costs by eliminating
those factors associated with land-based equipment, and the shorter pumping distance reduces
operating time and fuel consumption.
Limitations that must be considered are that some hopper dredges may be unable to access desired
shallow-water placement sites because of draft limitations. Alternatives include "light-loading,"
which reduces the vessel draft, and speciality shallow-draft hopper dredges. Pipeline discharging
into the nearshore may also be limited because of the more energetic hydrodynamic environment
closer to shore, which can create large forces on the pipeline.
Ultimately, projects considering nearshore placement of dredged material must optimize costs by
closely examining the dredging requirement, cost of available equipment specific to the project of
interest, type of nearshore feature desired, and volume of material to be dredged. In some cases,
the benefitting parties may have to contribute larger portions of the dredging and placement costs
to ensure that the desired feature is constructed with appropriate equipment if the selected equipment
or method is more expensive than the least-cost method.
SUMMARY: Planning and designing a dredging project with nearshore placement alternatives
first require knowledge of the physical and ecological environment. Engineering decisions can
then be made to determine potential placement alternatives that, in turn, provide a basis for decisions
driven by economic factors. The results of such decisions may provide a beneficial, economically
feasible nearshore placement alternative.
Under the DOER Program, investigations will be conducted in the Evaluation and Design of
Nearshore Placement of Mixed Sediments Work Unit to enhance opportunities for nearshore
placement of mixed sediments. Additionally, other work units in the Nearshore and Offshore
Placement Focus Area will include physical model investigations of mixed sediment movement,
improvement of existing numerical models determining the fate of dredged material, and environ-
mental effects of material placed in the nearshore. Benefits from this research will include improved
use of maintenance dredged material for shoreline stabilization, increased acceptance by regulatory
agencies of nearshore placement as a viable long-term disposal alternative, and lower costs for
overall maintenance dredging operations.
POINTS OF CONTACT: For additional information contact the authors, Mr. Gregory L. Wil-
liams (601-634-2089, williag3@ex1.wes.army.mil), and Ms. Terri L. Prickett (601-634-2337,
5
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |