|
|
ERDC TN-DOER-T7
October 2004
operations were included in the plant design, what are the impacts if 25-percent sand is
encountered? What costs would be anticipated in connection with this, including equipment
changes and dredging or processing interruptions? These are the uncertainties that drive costs of
remediation activities up. Defining the necessary actions and remedies in advance, to the extent
possible, allows better definition of the risk to all parties. It is to be hoped that this will have the
ultimate effect of reducing the cost of processing for mainstream materials treatment.
Sampling and testing to determine compliance with materials specifications should also be
carefully developed. The scale of material heterogeneity should be considered. Sampling
volume, location, frequency, and sampling and analytical methods must be explicitly specified.
Uncertainty associated with the sampling and analysis should be estimated and factored into
considerations. Material variations resulting from changes in operating conditions should also be
considered in specifying performance testing. For example, percent solids of the cake is a
commonly tested parameter for process comparison. However, percent solids in the cake is a
function of the compaction and dryness of the materials (% solids = mass solids/total mass), and
the specific gravity of the materials in the sample tested. Percent solids may be increased in
organic sediment by coarsening the cut at the front of the treatment train and allowing more sand
to report with the fines. The density of the cake would be higher, and permeability may be
improved, but the volume may also increase due to the higher mass reporting with the fines and
decreased material compressibility. Higher percent solids for materials of the same specific
gravity would indicate greater volume reduction. Testing of the cake should therefore also
include not only percent solids, but bulk density of the cake, specific gravity of the solids, grain
size distribution, and water content in order to fully determine the fate of materials and the
effectiveness of the process. Use of these factors in evaluating overall volume reduction was
discussed earlier in this document. Weight reduction can be estimated using the same
parameters.
Basis of Payment. Payment is typically specified in terms of cost per unit volume dredged.
Alternatively, payment might be specified in terms of cost per unit volume processed, or cost per
unit volume cake produced. The obvious disadvantage of the latter specification is that the
contractor will profit from maximizing the cake volume, which will likely be contradictory to
processing and cost reduction objectives. Chemical costs, however, should be correlated and
charged based on the volume or mass of fines processed, rather than the total volume of sediment
processed. For example, if sand content is higher than expected, chemical demand will be lower.
Chemical costs based on total sediment volume would not reflect this.
Process water normally requires treatment prior to discharge. If the dewatering contractor is
responsible for water treatment costs, this may motivate conservative water use and minimize the
volume of water to be treated. Emissions control, decontamination, and other site management
considerations will normally be encompassed in the agreement as well. Payment basis is
therefore an area which should be given careful consideration when developing performance
specifications.
COST: Unit treatment costs are a function of character and volume of the material to be
processed. Mobilization and demobilization costs are relatively insensitive to treatment volume;
small projects will therefore have a higher associated unit cost. Mechanical dewatering is
14
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |