restoration">
|
|
dredge, two on the RDB side of the channel and one on the LDB side across the
channel. Two anchors were set downstream of the dredge on the RDB side of the
channel (Figure 5). As a result, only one wire cable stretched across the channel.
Each cable was tensioned to test the corresponding anchor set. The
Beachbuilder's winches automatically advance at an adjustable, pre-set tension.
Several of the anchors did not hold when tension was applied to the associated
cable. The leverman continued testing the anchor-holding capacity until a
suitable combination of cable tension (approximately 1,200 psi) and power from
the push tug was determined to allow forward movement of the dredge. Once all
equipment was deemed operational, the mobility demonstration was initiated at
2145 hr on 5 June in Reach 1.
Beachbuilder
Anchor lines
Figure 5.
Initial Beachbuilder anchor deployment configuration
The Beachbuilder was moved out into the channel near the centerline (CL)
and back to the RDB side of the channel with no problems. The USACE,
Mississippi River Bar Pilot, and contractors all agreed that the dustpan's maneu-
verability with the flexible floating hose was adequate to proceed with the
demonstration. Actual dredging started at 2235 hr along the RDB side toe of the
channel in Reach 1. After 25 min pumping, instrumentation indicated possible
plugging of a portion of the dustpan. The dustpan was raised for inspection and
13
Chapter 2
Project Description
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |