restoration">

 

Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Method and mode of materials placement
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

waiting in the area may be an option. Detailed evaluation of the flexible-
discharge dustpan dredge mobility capabilities for sailing between dredging
regions is beyond the scope of this demonstration report.
Method and mode of materials placement
Under this factor, the dredging plant should be versatile enough to perform in
both open water placement and shore placement. As discussed above, the
Beachbuilder demonstrated a capability to conduct shore placement in a rela-
tively long pumping distance mode. Open water (overboard) placement was not
demonstrated during the demonstration.
Minimum-acceptable dredging rate per day
The controlling minimum dredging rates under this factor in the MVN report
for overboard and long distance pumping are 78,000 and 24,000 cu yd/day,
respectively. The overboard pumping configuration was not tested during the
demonstration. With respect to long distance pumping, the Beachbuilder
achieved an approximate average production rate of 27,800 cu yd/day pumping
222,100 cu yd (with pumping distances ranging from 6,550 ft to 10,820 ft) in
192 hr. The Beachbuilder pumped 10,000 ft or greater for approximately six out
of the eight demonstration days while working primarily on the RDB side of the
channel.
Capability for yielding to vessel passage
In the MVN report, the time projected for the dredge to yield to passing
vessels under this factor is 15 to 30 min. The HOP project demonstrated that
dredge downtime for vessel traffic is primarily a function of dredge position in
the channel, number of vessels passing, speed and direction of vessels passing,
and movement time required to allow safe passing clearance. The Beachbuilder
was able to continue dredging in the portion of the channel adjacent to the hard
point and submerged line with no downtime during passage of a single vessel by
dropping the cross-channel cable and raising it after vessel passage. Forward
movement into the cut was maintained during this period by the push tug. When
dredging on the far side of the channel, the Beachbuilder required approximately
11 min to clear the channel from one toeline to the other. This transit time would
be reduced the closer the dredge was working to the channel CL (less distance to
travel), and/or if only one deep-draft vessel was passing because the dredge
would not have to cross the entire channel to let the vessel pass. Total downtime
for vessel traffic may be minimized if discharge areas are available on both sides
of the channel. In the vicinity of Pass A Loutre, a discharge pipeline on the LDB
side may not be an option due to its use as a hopper dredge disposal site and the
potential hazard of a vessel grounding.
46
Chapter 6
Feasibility Analyses

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business