|
|
characterization and placement of the contaminated material, aspects re-
lated to the characterization and placement of the capping material, and as-
pects related to the capping site under consideration. Each of these
aspects must be initially examined in a parallel fashion (see Blocks 2, 3,
and 4 of Figure 2). Further, the interrelationship and compatibility of
these three aspects of the design are critical.
Characterize contaminated sediment (2)
The contaminated sediment must be characterized from physical, chemi-
cal, and biological standpoints. Physical characteristics are of importance
in determining the behavior of the material during and following place-
ment at a capping site. In situ volume (to be dredged), in situ density (or
water content), shear strength, compressibility, and grain-size distribution
are needed for evaluations of dispersion and spread during placement,
mounding characteristics, consolidation, and long-term stability and resis-
tance to erosion. These data should be developed using standard techniques.
Some chemical and biological characterization of the contaminated
sediment is normally performed as a part of the overall evaluation for suit-
ability for open-water placement. Guidance on characterization of con-
taminated sediments is found in Chapter 3.
Select a potential capping site (3)
The selection of a potential site for capping is subject to the same con-
straints and tradeoffs as any other open-water placement site. The major
considerations in site selection include bathymetry, bottom slopes, cur-
rents, water depths, water column density stratification, erosion/accretion
trends, proximity to navigation channels and anchorages, bottom-sediment
characteristics, and operational requirements such as distance to the site
and wave climate. However, in addition to normal considerations, the cap-
ping site should ideally be in a relatively low-energy environment with
little potential for erosion or disturbance of the cap. While capping at a
low-energy site is desirable, such sites are not always available. Higher
energy sites can be considered for dredged material capping, but a de-
tailed study of erosion potential is required; increases in cap thickness to
account for potential erosion or use of a coarser grain-size material may
be required.
Consideration should be given to the following factors during selection
of a potential capping site. Bathymetry forming a natural depression will
tend to confine the material, resulting in a CAD project. Placement of ma-
terial on steep bottom slopes should generally be avoided for a capping
project. Water column currents affect the degree of dispersion during
placement and the location of the mound with respect to the point of dis-
charge. Of more importance are the bottom currents, which could poten-
tially cause resuspension and erosion of the mound and cap. The effects
of storm-induced waves on bottom-current velocities must be considered.
For some sites, other processes such as prop wash may need to be consid-
ered. The deeper the water is at the site, the greater the potential is for
10
Chapter 2 Design/Management Sequence for Capping
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |