|
|
Conversely, it is much more difficult to control the rate sand is dis-
charged from a split-hull barge. Based on the Seattle District's experience
using split-hull barges to place caps, Parry (1994) recommends discharge
rates of 30 to 42 m3/min to reduce the size of the end pulse caused by
bridging to about 5 percent of the load. At higher discharge rates, say
600 m3/min, Parry (1994) notes that the size of the pulse can be up to
33 percent of the total load. Nelson, Vanderheiden, and Schuldt (1994)
report discharge rates of 41 to 70 m3/min using a split-hull barge at the
Eagle Harbor in situ capping project.
Controlling and monitoring extended discharge from a split-hull barge
is a nontrivial matter. The small barges, typically about 1,000 m3 used by
the Seattle District, are opened 6 to 8 deg to start sand flowing. Discharge
rate can be monitored by change in draft measured by pressure sensors
radio linked to a display on the tug, and with experience it can be done
visually. As the load is lightened, the barge has to be opened more to
continue a constant flow of sand.
Inspection and Compliance
Proper tracking of dredged material placement prior to capping includes
adequate records of barge position, environmental conditions, vessel head-
ings and velocities, start/end times of discharge, and load/draft of barge.
In most cases, dredging contractors keep records detailing much of this
information in their dredge logs.
The information from the inspector 's or contractor 's logs can be useful
in identifying volumes of material placed, locations of placement, and cor-
relation of material placement with hydrographic survey results. Dredge
logs can also be the primary source of information for locating material
that is short-dumped. Short-dumping can result for various reasons including
human error, inadequate positioning information, malfunction of electronic
positioning instruments, and safety. When material is short-dumped, it
usually ends up outside of the specified disposal site, and postdisposal sur-
vey information may be limited or nonexistent. However, the dredged ma-
terial must still be capped, and the more information that is available
(from dredge logs), the better the capping job that can be done. In one in-
stance on the Port Newark/Elizabeth project, a short dump of one barge
load of material (2,300 m3) was covered with 31,000 m3 of cap material
because of a substandard positioning system (LORAN-C), lack of knowl-
edge of the tug/barge offset (the antenna was on the barge not the tug),
and incomplete records.
Dredged material placement inspection can be conducted by onboard
personnel provided by either the USACE District or dredging contractor.
Many USACE dredging projects already require onboard inspectors to
document proper dredging location, volumes dredged, and appropriate
depths attained. For capping projects, both the New England Division and
the New York District use inspectors. New England Division inspectors
are contractors (but not employees of the dredging company). The New
York District uses Corps employees as inspectors.
49
Chapter 5 Equipment and Placement Techniques
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |