|
|
structures, to such a thickness that the lower portion of the ice gouges and
displaces the bottom sediments. The thickness of the ice buildup de-
creases as distance from shore increases. Also as water depth increases,
ice gouging will be less of a concern. For those locations where ice goug-
ing may be problem, e.g., in situ capping sites nearshore, local experts
should be consulted as to the locations where ice gouging occurs and the
depth of the sediments disturbed.
Another operational concern is anchoring. Vessel anchors have the po-
tential to disturb bottom sediments (as do trawlers). While most any loca-
tion in shallow water (say 30 m or less) is subject to potential anchoring,
for most locations where open-water dredged material placement sites are
located, anchoring to such a degree that cap integrity is impacted will be
extremely rare. The anchors used by recreational vessels typically only
penetrate the bottom 1 to 2 ft. The relative area impacted by anchors com-
pared with the size of a cap is very small. Also, when the anchors are re-
moved, the area disturbed by the anchor is quickly filled. This is not true
for anchors from large ships, which can penetrate up to 5 to 10 ft. Thus
an area where ships routinely anchor would be a very poor choice for a
capping project.
Another operational concern is the ability to place a relatively thin cap
layer. Until recently, open-ocean capping operations made the controlled
placing of small thicknesses (less than 30 cm) difficult. For many of
those projects, the minimum cap thickness for most projects has been on
the order of 75 to 120 cm (2.5 to 4 ft). Recent experience from the Port
Newark/Elizabeth project at the Mud Dump (Randall, Clausner, and
Johnson 1994) and Puget Sound capping projects (Nelson, Vanderheiden,
and Schuldt 1994; Sumeri 1995) has shown that the sprinkling techniques
developed were successful and that layers about 15 to 20 cm (0.5 to 0.75 ft)
thick can be placed with reasonable assurance (though at increased cost
due to increased operational controls).
The placement process will likely result in some unevenness of the cap
thickness. This unevenness should be considered in calculation of the vol-
ume of capping material required.
If any of the above factors are significant for the site under considera-
tion, an additional cap thickness component for operational concerns, To,
should be added to the design cap thickness.
Chemical isolation
If a design function of the cap is to control contaminant flux, the poten-
tial for short-term and long-term flux through the cap should be evaluated.
The need for such an evaluation is dependent on the types of contaminants,
the potential for contaminant impacts, site and operational conditions, and
other factors. For example, if the reason for capping is to isolate a sediment
that is nontoxic to benthic organisms and exhibits bioaccumulation only
marginally above that for a reference sediment, the isolation provided by
the bioturbation thickness component will likely provide sufficient con-
trol, and there is little reason to conduct a detailed assessment. Conversely,
72
Chapter 7 Dredged Material Cap Design
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |