Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Rotterdam Harbor
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

Marina del Ray material (Mesa 1995). Actual placement was initiated fol-
lowing completion of the berms, so the geotextile bags were not actually
required as a control measure; but the project proved to be a valuable field
demonstration of this innovative concept.
The sediments were dredged using a clamshell and placed in a split-
hull scow lined with two layers of geotextile (a nonwoven inner liner and
a woven outer shell) forming a container. Following completion of filling
of a barge, the geotextile material was brought over the top of the barge,
and the edges were sewn closed to form the completed container. Modifi-
cations were made to the scow bulkheads to reduce the width and length
of the filled volume to allow easier release of the filled bags.
The first geocontainer was filled with approximately 1,900 cu yd of
material. Because of drainage of the sandy sediment during transport and
subsequent bridging action, the first container failed to fall completely
from the barge. Water jets were finally employed to fluidize the material
and release the bag. Subsequent bags were only filled with approximately
1,300 cu yd, and additional fabric was used in forming the containers,
providing more "slack" in the containers to help with release. A total of
44 containers were placed (Figure 36).
All contaminated materials were successfully placed within the
subaqueous dikes, and the dikes have performed as intended. Bathymetric
and sediment profiling image camera monitoring confirmed that approxi-
mately 98 percent of the contaminated material was retained behind the
subaqueous dike, and that the thickest deposits immediately outside the
dike were generally less than 5 cm (the regulatory limit set for the project
in advance).
Rotterdam Harbor
As a consequence of local effluent discharge from chemical industries
sited around the 1st Petroleum Harbor in the Port of Rotterdam, the harbor
basin contained heavily contaminated material. Several options (upland,
open water, dredged pits, and confined behind a sheet-piled dam) were
considered for disposing of the contaminated material as described by
Kleinbloesam and van der Weijde (1983). The alternative finally selected
was a CAD project that consisted of excavating pits in the 1st Petroleum
Harbor, dredging the contaminated material, disposing of it in the pits,
and capping and lining the pit with clean material (Figure 37). The plan,
called the Putten Plan, had to be executed so that dispersion of pollutants
into the surface water and groundwater was very low, but acceptable. Spe-
cial dredging equipment was used for the disposal operation, and studies
were conducted to determine the dispersion of the contaminants.
The first dredge pit was 550 by 120 m at the bottom and was 15 m deep
with a capacity of 1.4 million m3. The silt from the pit dredging was dis-
posed at sea, and the sand was used at various landfill projects. Two addi-
tional pits were dredged; the contaminated dredged material was taken to
the first pit, and the clean material was used or discharged at sea. A third
122
Chapter 10 Case Studies

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business