|
|
To calculate required cap volume, it is recommended that the "full cap
thickness" volume (i.e., a level cap at full thickness) be computed over the main
mound and inner flanks. Up to an additional 10-20 percent of cap material
should be identified as possibly being required and should be available.
The required cap thickness over a few centimeters-thick mound apron can
become an important issue when one considers the volume (and cost) of cap
material required to cover mound aprons. Table H3 compares volumes and
dimensions from the Port Elizabeth/Newark project (which required a 1-m cap
over the entire contaminated mound) and two generic cap projects based on the
mounds shown in Figures H1 (0.9-m cap over the entire mound) and H2 (0.9-m
cap over the main mound and a 0.3-m cap over the apron). Volume calculations
show that over half (55.6 percent) of the 1,870,000 m3 (2,446,000 yd3 ) of mate-
rial placed at the Port Elizabeth/Newark mound covered the contaminated
mound apron, which contained about 12 percent of the contaminated material
volume. Table H3 also shows that in the generic mounds shown in Figures H1
and H2 (identical contaminated mound shapes), the total volume of cap material
material required is reduced by nearly 60 percent, from 847,200 m3
(1,108,100 yd3) to 347,800 m3 (454,900 yd3) when the required cap thickness
over the apron is reduced from 1 to 0.3 m. The volume required to cover the
contaminated apron reduces from 16.4 to 4.3 percent of total cap volume. The
dredging and cap placement over the wide area covered by the apron will, for
most projects, significantly increase the project costs. In rare instances where an
abundance of cap material is being dredged as part of an authorized dredging
project, the cap material can be considered "free." However, the capping project
must still cover the additional cost of precisely placing the cap.
For low levels of contaminants, bioturbation-induced mixing of the cap-
contaminated material and native sediment may be sufficient to reduce the
resulting level of contamination to an acceptable level. McFarland (in prepara-
tion)1 describes procedures that can be used to determine the effects of reduced
cap thicknesses over the apron based on bioaccumulation studies. For the sedi-
ments used on the Port Newark/Elizabeth 1993 project, McFarland (in prepara-
tion) found that a cap thickness to apron thickness ratio of 2:1 was sufficient to
reduce bioaccumulation of the contaminant of concern (dioxin) to acceptable
levels. The apron thickness for the Port Newark/Elizabeth mound ranged from
1 to 10 cm with a 5 cm averge thickness. Thus using McFarland's results, a cap
thickness over the apron of 10 to 20 cm would have been sufficient. Most of the
capped mounds created as part of the New England Division's capping program
have cap thicknesses over the apron of 20 to 50 cm.
Another issue impacting the amount of cap required is how far beyond the
known contaminated mound boundary to place cap material. Because the edge
of the cap will normally be located with a sediment profiling camera, the edge of
the contaminated material will normally be defined to a precision of about 50 m.
Therefore, it seems reasonable to place cap material such that the cap material
1
References cited in this appendix are listed in the References at the end of the main test.
H9
Appendix H Level-Bottom Capping Projects
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |