Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Dredging and Backfill Operations in a Hostile Environment
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

Dredging and Backfill Operations in a Hostile Environment
Category:
Production Monitoring
Description:
The Boston Rivers Project involved the construction of 55 diffusers on the ocean bottom, 10
miles offshore in Massachusetts Bay in 110 ft of water. The $93-million project for the MWRA
was undertaken as a joint venture of J.M. Cashman, a marine contractor from Massachusetts, and
Interbeton, a subsidiary of the Dutch HBG Group.
The project consisted of dredging, boring of vertical shafts, installation of risers and precast
diffusers, and armor rock placement. What is applicable to Corps dredging projects offshore is
beach restoration projects involving offshore borrow sources.
The work platform for the majority of the project construction was the Dredge "Lyons." The
Lyons is 120 ft in length, with a 55-ft beam, and a draft of 10 ft with 5 ft of freeboard. Stability
analysis of the dredge indicated that the rig could withstand a 3- to 4-degree roll from either
starboard or port, which was tested many times throughout the project duration. Stability from
bow to stern was adequate, provided the dredge was pointed into the direction of the wave attack.
The dredge was moored to the seafloor with a five-point anchor configuration.
A Project Installation Manual was used to provide strict quality control procedures for the
following:
1. ROV (remote observation vehicle) inspections.
2. Bathymetric surveys.
3. Dredging.
4. Protective dome movements.
5. Backfilling and landscaping.
6. Grout skirt placement.
7. Grouting of casting and skirts.
8. Underwater assembly of HPDEX domes.
9. Repairs to diffuser coating.
The project team monitored weather forecasts through faxes (commercial and public) to
continually modify schedules to maximize production.
Dredging was limited to sea conditions of less than 4 ft. The dredge used a computerized
positioning system, developed by SAIC, based on the Del Norte Range Range Microwave
system.
At the heart of the project was the heave compensation system. The TSS 320b heave
compensator was used. Bathymetric survey activities were central to dredging and backfill
material quality control. Bathymetric surveys were used to determine the existing seabed
elevation.
Reviewer:
J. Lally
Projects Completed:
Boston Risers Project
Location:
Massachusetts Harbor, Massachusetts
Project Contact:
Carlos Pena
Estimated Cost:
$93 million
Information Sources:
Literature:
Title:
"Dredging & Backfill Operations in a Hostile Environment"
Author:
Carlos Pena
Month:
10
Year:
1995
LitType:
Report/Proceedings
Publisher:
WEDA 16
54
Chapter 5 Other Technologies Reviewed

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business