Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Ijsseloog CDF Liner
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

ERDC TN-DOER-C18
August 2000
Lagoon (PIANC 1996, Consorzio Venezia Nuova 1997, Bernstein 1999
(Personal communication, 1999, Alberto Giulio Bernstein, The Tresse Island
Rehabilitation Project, Head of the Consorzio Venezia Nuova Environmental
Department.). A portion of the contaminated sediments was too contaminated
to be recycled for the reconstruction of marshes, and therefore was placed in
a lined and covered CDF on Tresse Island. This site was formerly used for  To view figure
the deposit of urban and solid waste, and the containment measures were  larger, click here
designed to isolate both the existing waste materials and future dredged
Figure 17
materials from the Venice lagoon waters. The isolation from the lagoon has
been achieved by the use of a reconstructed perimeter dike system. A cross-section of a portion of
the perimeter dike system is shown in Figure 17. Rock-fill berms with concrete topping were
constructed on the sides of the island exposed to wave action due to ship traffic. Sheetpiling sealed
with polyurethane was driven to a depth of -10 m into a thick, low-permeability soil layer to form
a vertical cutoff. Dry material was placed in a lined fill immediately landward of the sheetpile. A
secondary dike was constructed further landward with the liner incorporated into the dike cross-
section. In areas not exposed to ship traffic, a simpler "plastic diaphragm" consisting of mixture of
water, cement, and bentonite was constructed with a thickness of 0.5 m and to a depth of -8 m,
reaching clay layers to form a vertical cutoff. The entire perimeter system was covered with topsoil
and will be revegetated and planted with trees. The sealed perimeter dikes resulted in a large area
suitable for placement of new material dredged from canals and channels. Tresse Island is designed
to hold a total of 700,000 cu m of dredged material. Once filled, the site will be covered with a
clay layer to allow for revegetation.
Ijsseloog CDF Liner. The Ijsseloog CDF is a large island CDF constructed in Lake Ketelmeer
in The Netherlands. The site is designed to store approximately 21 million cubic meters of
contaminated material and incorporates several containment features and operational strategies
(Heineke, Eversdijk, and Kevelam 1997). The site was constructed in an area with existing bottom
contamination; therefore, temporary storage facilities for this material were required, and the
material was later re-handled into the completed CDF.
The configuration of the CDF was selected as a circular fill, consisting of a 40-m-deep excavated
pit, surrounded by a 10-m-high ring dike. This high fill with minimal surface area would maximize
consolidation resulting in a low permeability fill, and would minimize contact area with groundwater
flows. A 1-m-thick clay layer was placed in the bottom of the constructed subaqueous pit.
Fine-grained sediments underlying the ring dike were left in place (except for the contaminated
surficial layer) so that a low-permeability layer would remain beneath the dike. A seepage cutoff
layer was constructed in the under/inner part of the ring dike with a geomembrane to prevent seepage
from inside the CDF to surrounding surface water.
The water level within the CDF will be maintained at the same level as the hydraulic head in the
CDF foundation (-4.5 m) until the CDF fill reaches -8 m. The same strategy will be used once
consolidation brings the contaminated fill level again below -8 m. Note that a synthetic liner was
considered in the early design stages, but the environmental impact assessment (EIA) for the site
concluded that a liner was not necessary because of the high cost and difficult placement conditions.
Further, the EIA concluded that the failure of a liner within the period of 25,000 years after placement
10

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business