Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Terminal 3 Seattle CDF Cover
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

ERDC TN-DOER-C18
August 2000
The enclosed area was subsequently filled with contaminated sediment
dredged from the remaining portion of the bay with a cutterless pipeline
dredge. To avoid volatilization of mercury, a water pond of at least 50 cm was
maintained over the dredged material during the filling operations. After the
completion of dredging, a surface cover of soil was placed over the reclaimed
sediment for confinement. It was intended that the cover be placed under  To view figure
larger, click here
overlaying water; however, the sediment surface was too soft to be covered
with clean soil directly with equipment, and measures were needed to stabilize
Figure 22
the sediment to improve trafficability and bearing capacity. This was accom-
pished by first placing a synthetic fiber cloth and a net of ropes by workers in boats maneuvered by
cables (Figure 22). Once the fiber cloth and rope net were placed, the dredged material was
compacted by an 80-cm layer of sand placed hydraulically. A 1-m-thick layer of volcanic ash earth
of low specific gravity (1.1 in the air) was then spread using small bulldozers.
Terminal 3 Seattle CDF Cover. Several nearshore
CDF sites in the Puget Sound, WA, region have been
capped with clean material and converted to container
facilities or parking areas (Palermo et al. 2000; Boat-
man and Hotchkiss 1997; Converse Consultants 1992).  To view figure
To view figure
larger, click here
One example is the Terminal 3 site in Seattle which  larger, click here
was capped upon completion of the CDF fill. The
specification for the cap material was for select struc-
Figure 23
Figure 24
tural fill to support the pavement section. The material
was likely sand and gravel from a nearby quarry. The contractor placed the initial lift of material
using a conveyor (Figure 23). After several meters (feet) were placed in this manner, the remaining
cap section was pushed into place with dozers (Figure 24).
Sunny Point CDF Slurry Wall. A slurry wall was constructed at an upland
CDF on the U.S. Army facility at Sunny Point, NC (Figure 25). This slurry
wall was required to control saltwater intrusion into a sand aquifer underlying
the site. Water was ponded to within 1.8 to 2.4 m of the dike crest and held at
that level, presumably to maintain good water quality for the effluent dis-
charge. However, this produced a static head, resulting in saltwater intrusion  To view figure
larger, click here
into the aquifer, which eventually impacted a number of large and historic
trees on property adjacent to the CDF. This was a nontypical groundwater
Figure 25
intrusion problem, in that the contaminant of concern was chloride (salinity),
which is highly mobile, and does not adsorb to dredged material or foundation soil particles, as do
most contaminants of concern found in sediments.
A cutoff slurry wall was constructed along the land side of the CDF near the dike toe to correct this
problem. The wall was constructed to a depth of approximately 18 m using a long reach backhoe
and a "traveling slurry pond." A grout mixture was prepared in a bermed pond, and the backhoe
excavated sections of the wall within the bermed pond, allowing the grout to fill in the trench as
excavation progressed. Slurry was added and the pond was "shifted" to travel along the slurry wall
alignment until the wall was completed. The completed width of the slurry wall is 0.6 to 0.9 m.
13

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business