Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Penns Grove CDF Slurry Wall
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

ERDC TN-DOER-C18
August 2000
Once the wall was completed, wells were pumped on the outside of the wall to recover chloride
plumes down gradient from the wall. Piezometer data indicated that the groundwater flow was
reversed, and the pumping drained several small ponds. Pumping was therefore discontinued when
the majority of the plume was recovered (Personal communication, Les Wyatt, Wilmington District,
1999, Chief, Design Section, Engineering Branch, Technical Services Division).
Penns Grove CDF Slurry Wall. A slurry wall was constructed at the Penns Grove CDF located
adjacent to the Delaware River near Penns Grove, NJ (USACE Philadelphia District 1981). This
136-ha CDF was sited on an extensive sand and gravel foundation. Private contractors mined sand
and gravel for resource recovery and creation of additional disposal capacity within the CDF prior
to any placement of dredged material under a lease agreement with the Philadelphia District. This
operation removed large portions of the surficial silts and clays, exposing the underlying aquifer to
potential infiltration of leachate from the CDF. The mining operation was terminated when leachate
effects were identified as a potential problem.
A cutoff slurry wall was subsequently constructed outside the disposal area
dikes and exterior drainage trench as shown in Figure 26. The trench had a
minimum width of 1 m (3 ft) and was cut to depths of 9 to 18 m (30 to 60 ft)
and keyed into an impervious clay layer underlying the site. A mixture of 70
parts sand, 30 parts silt, and 2 parts bentonite was used. The total length of
trench was approximately 3,400 m (11,000 ft), extending generally around two
To view figure
larger, click here
sides of the CDF. Silt layers are intact along the remaining two sides that
would substantially reduce infiltration. Monitoring wells were also installed.
Figure 26
This site has not yet been used for dredged material placement.
Monroe Harbor CDF Dike Mattress. A grout mattress was used at a CDF located at Sterling
State Park to seal prepared limestone dikes. The goal was to make the CDF watertight because of
concern for groundwater contamination due to PCB concentrations in the dredged material. The
original design included a bentonite seal on the bottom and side slopes of the CDF. The bottom
and most of the slope were to be under water because of the proximity to Lake Erie. The bentonite
was removed from the design during a value engineering review due to the difficulty expected in
placing the material under water. A grout mattress was substituted for the side slope, and additional
clay was left on the bottom. The mattress was put in place, but it tended to float due to Lake Erie
flowing into the CDF. To stop that from occurring, a clay seal was constructed on top of the mattress
to hold it in place. The clay sealed the mattress and dike successfully. As with other CDFs with
prepared limestone dikes, once dredged material is placed against the dike, it becomes watertight.
The mattress's primary benefit is to prevent erosion on the side slopes until dredged material can
be placed against the slopes (Personal communication, Doug Zande, Detroit District, 1999, Chief,
Operations Technical Support Office).
Waukegan Harbor (Outboard Marine Corporation Superfund Site) Dike Cutoff. PCB-
contaminated sediment from Waukegan Harbor was dredged hydraulically and placed in contain-
ment cells constructed in a boat slip and other nearshore areas. Design of these cells included a
double sheetpile cutoff wall to isolate the slip from the harbor and a clay slurry wall that was
anchored to the underlying clay till (see Figure 27). The slip held approximately 23,000 cu m of
contaminated sediment (USEPA GLNPO 1998).
14

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business