|
|
ERDC TN-DOER-C27
July 2002
APPENDIX C
PROJECT EXAMPLES1
Example 1
The first example compares costs for the following six dredging and disposal alternatives for a
one-time project, such as a remediation action, with a 2-year period of analysis:
1. Hydraulic dredging, CDF disposal
2. Hydraulic dredging, sand separation, CDF disposal of fines
3. Hydraulic dredging, sand separation, CDF placement of dewatered fines
4. Hydraulic dredging, sand separation, dewatering and offsite disposal of fines
5. Mechanical dredging, CDF disposal
6. Mechanical dredging, offsite disposal
Dredging costs are applied to in situ project volume. Separation, dewatering, and transportation
costs are applied to processed volumes or weights. Unit CDF construction costs are based on
sediment storage requirements, and are adjusted upward for alternatives requiring higher dikes to
provide freeboard and ponding volume. For each alternative, a total project cost is calculated,
including dredging, processing, transport, and disposal costs. These costs are then converted to a
project cost/year, based on the duration of the dredging (Tables C1, C3, C5,...C11). Costs for CDF
construction and closure capping are also calculated. Interest during construction is then calculated
for each alternative and applied to the annual project costs, plus CDF construction and capping
costs, which are added to the annual project costs in the respective years in which they occur
(Tables C2, C4,...C12). This gives a Total Financial Investment cost for each alternative, which is
the basis for the economic comparison of each alternative. The least-cost CDF disposal alternative
without separation (mechanical dredging, CDF disposal) is the base condition. The results of this
analysis indicate that, for the assumptions made, a negative benefit is derived from the use of
separation, where mechanical dredging and CDF disposal is an alternative (Table C13). A positive
benefit is seen where offsite disposal is required. For separation alternatives, beneficial use of sand
with no associated transport or disposal costs is assumed. No real estate acquisition is included in
CDF construction costs, as the site is normally provided by the sponsor and is not a government
expense.
1
To convert measurements given in tons in these examples to kilograms, multiply by 907. To convert
measurements given in cubic yards to cubic meters, multiply by 0.7645.
21
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |