restoration">

 

Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Dredge Operational Requirements
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

Dredge Operational Requirements
Dredge to a minimum depth of 60 ft below the water surface resulting in
a minimum channel depth of -51 ft mean low gulf (MLG).
Pump the dredged material up to a total distance of 15,000 ft.
Achieve competitive dredging production rates with stoppages required
for normal vessel traffic passage.
Navigational Requirements
Utilize total length of flexible floating pipe during dredging and moving
up and down, and across the channel.
Maneuver into desired dredge cut both cross channel (across the total
channel width) and longitudinally (up and down the channel).
Maneuver dredge safely to allow for normal vessel traffic passage.
Dredged Material Discharge/Placement Requirements
Establish discharge pipeline across dike, adjacent pasture, and existing
wetlands to designated placement point(s) (see Figure 2) with minimum
possible impact on existing marsh.
Install and operate discharge pipeline with minimal leaks in existing
marsh.
Secure discharge pipeline in current using anchor system.
Operate and safely maneuver discharge pipeline in the Mississippi River
under typical conditions to allow for passage of both shallow-draft and
deep-draft vessels.
Pump and place dredged material so as to create a suitable marsh area
with minimal impact to existing marsh.
It was determined that the evaluation of these requirements was the key to
determining demonstration success, and for assessing the feasibility of imple-
menting this technology in future maintenance dredging programs for this area.
Dredging activities were to be conducted in the spring of 2002 to coincide
with the normal period of high water on the Mississippi. The dredge was to
operate over a continuous 5-day period, 24 hr per day, with an option for up to
3 additional days of dredging based on the success of the project and time
required to meet the project requirements. The first 24-hr period of operation was
to consist of equipment mobility demonstration and equipment checkout.
ERDC enlisted the assistance of OA Systems Corporation (OAS) to provide
support in developing the project and conducting the field activities. Based on the
SOW requirements, OAS determined that the Beachbuilder was the only
U.S.-owned dustpan dredge with the required pumping capabilities. Under the
existing OAS task order contract, a rental agreement with Weeks Marine, Inc.,
4
Chapter 1
Introduction

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business