restoration">

 

Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Beachbuilder
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

was negotiated for use of the Beachbuilder in the demonstration project. Several
meetings and numerous telephone conferences were conducted including MVD,
MVN, ERDC, OAS, Weeks Marine, and the Associated Branch Pilots (Bar
Pilots) from the Port of New Orleans personnel to define and concur on proposed
field activities. It was suggested and agreed that River Pilot Association pilots
would be hired to man the Beachbuilder pilot house on a 24-hr basis to monitor
vessel traffic and keep the leverman appraised of vessel traffic movement.
Having a pilot onboard during the entire demonstration while the dredge was
operating (a condition not usually required for hydraulic pipeline dredging
contracts) helped ensure the safety of dredge and crew, and allowed the pilots an
opportunity to observe and comment on the feasibility of this type of dredging
methodology. OAS and Weeks Marine prepared a proposal for the demonstration
project. A delivery order was issued to OAS in March 2002 to begin the project.
A meeting was held at the MVN office on 8 March 2002 with MVN, ERDC,
OAS, and Weeks Marine personnel in attendance. Final technical details of the
project were discussed and directions given as required on right-of-way, dredging
reaches, anchor lines, pipeline placement, safety requirements, visitors, opera-
tions data, surveying, and assignment of MVN Area Office inspectors. The site
activities were originally scheduled for late April or early May 2002. The project
was delayed due to resolution of funding issues, repair and maintenance on the
Beachbuilder, and availability of the floating hose, which was being used on
another project. Weeks Marine installed new bow winches and high strength wire
rope on the Beachbuilder in preparation for the demonstration project.
Weeks Marine started mobilizing equipment to the project site during the last
week of May 2002. A project kick-off meeting was held at the Venice Area Sub
Office on 3 June 2002 and included MVN, OAS, and Weeks Marine personnel.
Project activities, schedule, and safety issues were discussed. Recent surveys of
the project area conducted by MVN were presented. Based on the shoaling
detailed in the survey results, three channel reaches were identified and priori-
tized for dredging operations (Figure 2). Prioritization was based on physical
location of the reach and minimizing the requirement for movement of the
submerged line. The northernmost reach at the head of the bend in the channel at
the HOP was identified for initiation of the equipment mobility demonstration.
Vessel traffic in this area generally steered in a straight line prior to initiating a
turn through the bend, and thus was deemed somewhat safer with respect to
vessel traffic flow and proximity of the vessel traffic to the Beachbuilder while
dredging in the channel. Once it was demonstrated to all concerned parties that
the Beachbuilder could safely maneuver back and forth across the channel,
Beachbuilder was to move downriver and work in a reach located in the bend
where greater shoaling generally occurs. At the conclusion of the meeting,
Weeks Marine was directed to initiate site activities in preparation for dredging.
5
Chapter 1
Introduction

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business