restoration">

 

Order this information in Print

Order this information on CD-ROM

Download in PDF Format

     

Click here to make tpub.com your Home Page

Page Title: Dredge Maneuvering Characteristics
Back | Up | Next

Click here for a printable version

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Combat
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
USMC
   
Products
  Educational CD-ROM's
Printed Manuals
Downloadable Books
   

 

Dredge Maneuvering Characteristics
The dredge maneuvering characteristics were determined by calculating the
respective characteristic components from data reduced from several sources,
including: the contractor's daily dredge report and daily submittals on Engineer
Form 4267 "Report of Operations Pipeline, Dipper, or Bucket Dredges,"
supplemental notes taken by USACE and contractor personnel, and from the
time-series data of the dredge or dustpan x-, y-, z-position and slurry density and
velocity. Some minor time discrepancies were noted between these different data
sources. These discrepancies are due primarily to different personnel manually
logging the entries at different times.
Relocating the hard point
The time interval for moving the hard point from Reach 1 to Reach 2 that
consisted of adding 3,600 ft of submerged line was 43 hr 45 min (time from
dredge shutdown at 1645 on 6 June to startup at 1230 on 8 June). To determine a
"typical" time interval that could be used for future project planning and esti-
mating, this interval should be adjusted by evaluating the effects of two factors:
work was suspended during the hours of darkness due to crew safety concerns of
this first-time demonstration, and the move was made before it was scheduled
because of the request to relocate the dredge due to the rapidly developing shoal
(described in Chapter 2). Once experience is gained on operating at night and a
safety hazard risk analysis is performed, the night-time operating restriction may
be lifted. The amount of time that work was delayed (due to darkness) on moving
the hard point consisted of 5 hr 18 min on 6 June, 10 hr on 7 June, and 5 hr
45 min on 8 June, for a total of 21 hr 3 min. The subtraction of the night-time
hours from the total interval results in 22 hr 42 min to float the submerged line
(fill with air), disassemble, add sections, and move the hard point. This time
could have been further reduced if the contractor had planned for the move by
having the additional pipe connected and standing by. The contractor estimated
that had the move been planned with the additional submerged pipe and handling
equipment standing by, the total time to move the fixed point would have taken
approximately 12 hr.
Anchor handling
The anchors were handled for three basic reasons during the demonstration:
to initially set them in Reach 1, to reposition anchors that were dragged during
the tension-setting tests and during dredging, and to reposition the anchors in
Reach 2. There was one instance where the cross-channel anchor outside the
LDB channel toe was impeding a hopper dredge placing material into the
disposal site in Pass A Loutre, and the anchor was promptly repositioned. The
anchor-handling times depended on the availability of the tugs, where the
anchors were being moved from and to, vessel traffic impacting the cross-
channel anchor handling, and (where precise anchor positioning was required,
i.e., ensuring the anchor was placed outside the channel) availability of the
survey vessel. Seven anchor-handling events were logged. Durations ranged from
24
Chapter 4
Dredging Operational Characteristics Analyses

Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business