restoration">
|
|
c. When moved for passing vessels, the dredge was usually relocated to
enable it to keep dredging with as little downtime as possible rather than
standing by for vessel traffic. The decision to relocate to dredge another
position was influenced by the number of deep-draft vessels and the
times between passings. If just one vessel was going to pass, the dredge
could move aside, then immediately reoccupy the same digging position,
but if several vessels were going to pass within a short time, then the
dredge would start digging in a new location.
On 11 June when the Beachbuilder was dredging the high spots in the nega-
tive ranges (total time of 10 hr 20 min), it took 55 min to reposition the dredge
six times (average of 9.2 min per move), and 5 min of downtime was due to a
delay from hopper dredge maneuvering. This resulted in a vessel delay
percentage of approximately 9 percent.
During the total demonstration duration (192 hr), a total of 8 hr was logged
as delay due to vessel traffic (4.2 percent of the total). During the last five
demonstration days (after relocating to Reach 2) when the crew had become
more familiar with this dredging method and dredging operations were more
routine, the logged vessel delay time (2 hr 29 min) consisted of 2.1 percent of the
total 117 hr available.
Time required to back the dredge down and reposition (reset)
for each cut
The time required and distances traveled to back down and reposition the
dredge for successive cuts were calculated from the resets identified in the daily
dredge logs by station and range. These resets' start and stop positions, linear
distances, respective times, and transit speeds are shown in Table 3. Entries that
included additional tasks completed along with the reset (i.e., add pipe, clean
dustpan, etc.) were excluded from these calculations due to the intent to calculate
an average transit speed based solely on reset time. Reset speeds ranged from
9 ft/min to 198 ft/min. The average reset speed for 37 resets was 74 ft/min, with a
median of 55.5 ft/min. The total time required to conduct these maneuvers was
5 hr and 20 min. One reason for the wide range of speeds is that on some of the
setbacks the floating hose required more repositioning by the tugs. Three resets
and respective times were identified from the daily dredge report that included
additional tasks, i.e., adding shore pipe that increased the total time for resets to
7 hr 10 min.
Cross-channel maneuvering capabilities
The ability of the dredge to move (laterally) across the channel is a major
element in analyzing this type of dredge's operational feasibility regarding
navigation safety. Table 4 lists 14 individual lateral moves made by the
Beachbuilder during the demonstration. These lateral moves are described by
respective date, start/stop times and positions, linear distance traveled by the
dredge, move time, and transit speed. The time used to calculate transit velocity
28
Chapter 4
Dredging Operational Characteristics Analyses
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |