|
|
ERDC TN-DOER-C27
July 2002
alternative. Alternatives with positive net benefits (a.k.a. BCR 1) are economically efficient
alternatives. The alternative with the greatest net benefits maximizes benefits.
Step 2: Calculate average annual cost. Although specifics will vary between sites and the
alternatives being evaluated, the economic analysis essentially follows the same series of steps.
These are described in the following paragraphs. The analysis can be readily incorporated into a
spreadsheet, facilitating comparison of several alternatives. This has been done for two examples,
which are included as Appendix C.
I.
Project Assumptions. This might include type of work, available disposal capacity, and base
condition, for example:
a. Type of dredging: new channel construction followed by maintenance dredging over
the period of analysis.
b. Disposal alternatives: no existing CDF.
c. Base condition: CDF disposal, without separation or mechanical dewatering (no material
will go offsite).
II.
Calculate Base Condition
a. Develop initial construction/dredging costs. These will be engineering costs, including
all items that will impact the total project costs. Such items include mobilization/
demobilization, dredging, dewatering, transportation, and placement. Any associated
costs, such as CDF construction or expansion required to accommodate the initial (new-
work construction) dredged material, must also be included in the construction costs.
(Existing capacity is treated as a sunk cost, and is not factored into the evaluation.)
Establish a construction period, annual quantity dredged, and total annual construction
cost.
b. Calculate interest during construction (IDC). IDC is the value adjustment of pre-base
year construction costs, and is an economic cost that will not actually be paid by any party
involved with the project. (In economic analyses, the base year refers to the first full year
the project is operational.) IDC should be applied to all construction costs, including all
costs associated with channel dredging as well as any placement costs, such as CDF
construction or expansion. (Sunk construction costs for an existing CDF are not
considered pre-base construction costs. Costs for a CDF constructed specifically for the
project defined for the period of analysis are considered pre-base construction costs.) The
calculation is done to bring all construction costs to the base year and make them
equivalent in their time value. IDC should be calculated using the formula:
IDC = P * (1 + i)t - P
(1)
where
P = Annual construction amount
i = Federal discount rate
t = Time (years from construction year to base year)
6
|
Privacy Statement - Press Release - Copyright Information. - Contact Us - Support Integrated Publishing |